BAU 2027 Stand Builder Checklist: What to Lock In Before the 11–15 January Build-up

Preparing a stand for BAU 2027 in Munich means coordinating design, production, technical approvals and transport, and the window is short. The fair runs from 11 to 15 January 2027 at Messe München, with build-up starting on 4 January. For international exhibitors it is tighter still, because components may be made in another country, trucked to Munich and installed inside the venue’s access hours. A BAU 2027 stand builder keeps those pieces moving together and cuts down last-minute surprises.

Here is what to lock in before the build-up starts.

BAU 2027 dates and build-up schedule

Event DetailBAU 2027
Exhibition Dates11 to 15 January 2027
VenueMesse München, Munich
Build-up4 to 10 January 2027
Dismantling15 January (from 18:00) to 19 January 2027
Visitor Hours09:30 to 18:00
Confirm your hall, stand number and the official hall plan first. Your hall location, neighbouring exhibitors and access arrangements all affect the design and the installation.
Set-up runs from 4 to 9 January, 07:00 to 23:00, and on 10 January from 07:00 to 18:00. Hall B0 has slightly different times on the last day, so check the official logistics page. On 10 January all vehicles must leave the grounds by 18:00, and decorating can continue until 20:00. Dismantling starts at 18:00 on 15 January and ends on 19 January. Stand-building vehicles cannot enter before 18:00 on the 15th, and early dismantling is not allowed and can carry a penalty of up to €5,000.

Six weeks out: what to finalise now

As of 23 November 2026, build-up is about six weeks away. That is why booking a stand builder early for a 2027 trade show matters: this is the time to finish decisions and check progress, not to start a new concept.

1. Confirm your location and size. Check the hall and stand number, total area, open sides, orientation, neighbours and any venue limits. These decide where walls, counters, displays and meeting areas can go.

2. Approve the final 3D design. Lock the counter, branded walls, displays, storage, meeting areas, lighting and screens. Changes after production starts hit fabrication and delivery.

3. Check production status. Ask for an update on structure, furniture, graphics, lighting and electrics, screens, quality checks and packing, and flag missing or late items now.

4. Sort your technical orders. The deadline for technical orders through the exhibitor shop was 11 November 2026. If you have not ordered electricity, rigging or other technical services, contact the Technical Exhibitor Service (tas3@messe-muenchen.de) straight away. Do not assume late orders will be accepted, and short-notice orders carry surcharges. Messe München also lists new rigging requirements for BAU 2027, so check them if you plan hanging elements.

Stand approval and technical rules

Your stand must follow Messe München’s technical guidelines and the conditions for BAU 2027. The same logic applies at other fairs, as the stand construction rules in Germany on permits, heights and fire safety show, but always work from the BAU documents. Booking space also does not include a stand, so check what your package covers.
You need to submit stand plans to the Technical Exhibitor Service when:
Plans usually mean floor plans, elevations, sections and any extra technical information requested.
Pay attention to fire-rated materials, safe electrics, stable connections, clear exits and escape routes, and safe installation of lighting and hanging elements. If the stand holds machinery or heavy samples, plan their position and handling before production. Anything overhead, such as signs or lighting trusses, needs coordination with the venue’s technical team.

What your builder should manage in production

Even with an approved concept, fabrication needs coordination, especially for a custom exhibition stand with counters, display units, branded walls and meeting rooms. Your builder should handle:

Shipping your stand from Poznań to Munich

For a stand produced in Poznań, transport has to be planned alongside fabrication, not after it. Components must reach Munich inside the build-up window, so plan around production completion dates, packaging and loading, vehicle availability, transport documents, delivery slots, unloading and on-site storage. Do not aim for the last build-up day, and leave room for delays.

Every shipment must carry the event name, exhibitor name, hall and stand number and the venue address (Messegelände / Willy-Brandt-Allee, 81829 Munich). Messe München does not accept deliveries on behalf of exhibitors, so use your own forwarder or an authorised one. If any goods come from outside the EU, sort out freight, customs and ATA Carnet paperwork before the truck leaves.

Tie the transport plan to the installation team. They should know when materials arrive, who receives them and how unloading works. For trucks over 7.5 tonnes, use the FairLog system to avoid long waits.

Checklist before build-up

Use this list before materials leave for Munich. It also fits into a wider trade show planning checklist for the rest of your exhibition calendar.

Conclusion

Six weeks is enough if decisions are made now. Confirm approvals, production status and transport, and keep every deadline in view. If you need an exhibition stand builder in Munich to pick up the project, send Aars Worldwide your hall number, stand size and brief.

Frequently Asked Questions

When does BAU 2027 take place?
From 11 to 15 January 2027 at Messe München. Build-up starts on 4 January.
On 4 January 2027, 07:00 to 23:00 daily until 9 January, then 07:00 to 18:00 on 10 January. Hall B0 has slightly different times on the last day.
Yes, if it is over 3 metres high, over 100 square metres, has covered areas or exhibits a vehicle. Otherwise plans are not usually required, but check the BAU documents.
Yes. Plan transport, delivery slots, unloading and installation around the venue’s official schedule.
Your hall and stand number, dimensions, stand configuration, branding, display and technical needs and your budget.