Preparing a stand for BAU 2027 in Munich means coordinating design, production, technical approvals and transport, and the window is short. The fair runs from 11 to 15 January 2027 at Messe München, with build-up starting on 4 January. For international exhibitors it is tighter still, because components may be made in another country, trucked to Munich and installed inside the venue’s access hours. A BAU 2027 stand builder keeps those pieces moving together and cuts down last-minute surprises.
BAU 2027 dates and build-up schedule
| Event Detail | BAU 2027 |
|---|---|
| Exhibition Dates | 11 to 15 January 2027 |
| Venue | Messe München, Munich |
| Build-up | 4 to 10 January 2027 |
| Dismantling | 15 January (from 18:00) to 19 January 2027 |
| Visitor Hours | 09:30 to 18:00 |
Six weeks out: what to finalise now
1. Confirm your location and size. Check the hall and stand number, total area, open sides, orientation, neighbours and any venue limits. These decide where walls, counters, displays and meeting areas can go.
2. Approve the final 3D design. Lock the counter, branded walls, displays, storage, meeting areas, lighting and screens. Changes after production starts hit fabrication and delivery.
3. Check production status. Ask for an update on structure, furniture, graphics, lighting and electrics, screens, quality checks and packing, and flag missing or late items now.
4. Sort your technical orders. The deadline for technical orders through the exhibitor shop was 11 November 2026. If you have not ordered electricity, rigging or other technical services, contact the Technical Exhibitor Service (tas3@messe-muenchen.de) straight away. Do not assume late orders will be accepted, and short-notice orders carry surcharges. Messe München also lists new rigging requirements for BAU 2027, so check them if you plan hanging elements.
Stand approval and technical rules
- The stand or advertising height is over 3 metres
- The stand size is over 100 square metres
- The stand has covered areas
- A vehicle is exhibited, which also needs a preventive fire protection application
What your builder should manage in production
- Final drawings: accurate measurements, structure, elevations, materials and electrical needs that match your allocated space
- Fabrication: every part made to the approved drawings
- Graphics: correct sizes, colours, resolution and placement, with logos and product names visible from the main visitor approaches
- Lighting and AV: screens and fixtures that suit the final layout, tested before transport where possible
- Pre-assembly: key parts assembled before dispatch to catch missing pieces and wrong measurements
Shipping your stand from Poznań to Munich
Every shipment must carry the event name, exhibitor name, hall and stand number and the venue address (Messegelände / Willy-Brandt-Allee, 81829 Munich). Messe München does not accept deliveries on behalf of exhibitors, so use your own forwarder or an authorised one. If any goods come from outside the EU, sort out freight, customs and ATA Carnet paperwork before the truck leaves.
Checklist before build-up
- Hall, stand number and dimensions confirmed
- Final 3D design approved
- Drawings submitted where required
- Fabrication completed
- Graphics printed and checked
- Furniture, counters and storage ready
- Power and lighting arrangements confirmed
- Screens and AV tested
- Transport booked with delivery slots
- Crew and build-up schedule confirmed
- Dismantling and return transport arranged
Conclusion
Six weeks is enough if decisions are made now. Confirm approvals, production status and transport, and keep every deadline in view. If you need an exhibition stand builder in Munich to pick up the project, send Aars Worldwide your hall number, stand size and brief.